The U.S. Army will miss its initial goal of receiving the first MV-75 Cheyenne II long-range assault tiltrotor for testing by the end of this year, according to the service’s acquisition office.

“Delivery of the MV-75 for testing will not occur by the end of 2026. The program made deliberate efforts toward this goal while making measurable program progress,” a spokesperson for the Assistant Secretary of the Army for Acquisition, Logistics and Technology (ASA(ALT)) said on Nov. 20. Despite the setback, the spokesperson emphasized that the service remains on track to complete development and testing in roughly half the time of comparable historical programs.

In January, then-Army Chief of Staff Gen. Randy George had projected that the service would accept a test airframe before the end of 2026. The Army has not yet set a new delivery date and is currently working with prime contractor Bell—a Textron subsidiary—to build an updated, resource-loaded integrated schedule and risk analysis to establish realistic milestones.

Summer Funding Shortfall Halts Communications

The missed milestone stems from a funding gap that surfaced earlier this year after the Army exhausted nearly all of its available fiscal 2026 MV-75 funding by July, according to Textron’s latest quarterly filing. During the shortfall, formal communications between the Army and Bell came to a halt, with Bell choosing to continue certain activities at its own risk while scaling back spending.

To bridge the gap, the Army requested in July to reprogram $350 million toward the program to support the construction and testing of eight prototypes. Congress approved the shift in the third quarter, allowing normal contract execution and communications to resume on Sept. 28. Textron CEO Lisa Atherton noted during an October earnings call that roughly $300 million was committed in contract changes to cover costs already incurred by the company and its suppliers.

FY27 Budget Uncertainty Clouds Initial Production

Further schedule pressures loom over the fiscal 2027 budget. The Army has requested more than $2 billion in discretionary funding for the MV-75 in FY27, but starting the fiscal year under a continuing resolution could delay the aircraft’s first low-rate initial production (LRIP) contract. Textron CFO David Rosenberg warned in October that the budget impasse could push the LRIP award past its previously anticipated window of late this year or early next year.

The latest slip follows months of schedule caution—including remarks in April from then-Program Acquisition Executive for Maneuver Air Maj. Gen. Clair Gill, who declined to commit to specific dates for first flight or production. Still, Army leadership maintains that the tiltrotor is indispensable. Selected in late 2022 to gradually replace portions of the UH-60 Black Hawk fleet, the MV-75 is designed to fly “twice as fast” and “twice as far” as existing Army assault helicopters.

“Getting the MV-75 into the hands of Army aviators will be the culmination of one of the biggest Army acquisitions,” said Army Undersecretary Michael Obadal. “The Cheyenne meets the endurance and close combat demands of large-scale combat operations… It’s a priority for the joint force.”